Throughout 2016, land acquisition for toll roads averaged 60 percent. Approximately 92 percent of the planned land for the Trans-Java Toll Road had been acquired by 2016, a 27 percent increase from the previous year, which only reached about 65 percent completion. Furthermore, land acquisition for the Trans-Sumatra-Sulawesi Toll Road and Non-Trans-Java Toll Roads reached 66 and 53 percent respectively. For the Jabodetabek Toll Road, only 32 percent of the land has been acquired.
Land acquisition for toll roads typically takes a long time. Two institutions coordinate in the land acquisition process: the Land Acquisition Team (TPT), comprising several components, and the National Land Agency (BPN) responsible for surveying.